The Real Math: TI Allowance vs. Turnkey vs. Unused TI

5,000 SF Office Build-Out — TI Allowance vs. Turnkey vs. Unused TI Value
SCENARIO: 5,000 SF Class B Office, 6-Year Lease
Base rent: $38.00/sf/yr = $190,000/yr = $15,833/mo
Tenant's planned build-out: Private offices, open workspace,
conference room, reception, breakroom
Tenant's construction budget estimate: $325,000 ($65/sf)

OPTION A: TI ALLOWANCE AT $75/SF
TI allowance: $75.00/sf × 5,000sf = $375,000
Tenant controls construction; hires contractors directly
Tenant manages project timeline and budget

Scenario A1: Actual construction cost = $325,000 ($65/sf)
Reimbursable under TI (up to $375K): $325,000
Unused TI balance: $375,000 - $325,000 = $50,000

IF LEASE SAYS "POCKET IT" (rent credit or cash):
Tenant receives $50,000 as rent credit (applied to
first 3.1 months of rent: $50K ÷ $15,833/mo)
Net effective TI value: $375,000 (all captured)

IF LEASE SAYS "LOSE IT" (forfeited unused balance):
Tenant receives only $325,000 of $375,000 committed
Lost TI value: $50,000 (forfeited back to landlord)
Net effective TI value: $325,000

Scenario A2: Actual construction cost = $400,000 ($80/sf)
Reimbursable under TI: $375,000 (cap)
Tenant-funded overage: $400,000 - $375,000 = $25,000
Net effective TI value: $375,000 (cap reached)

OPTION B: TURNKEY AT $90/SF
Landlord commits to deliver 5,000 SF fully built to specs
Landlord value of build-out commitment: $90/sf × 5,000sf = $450,000
Tenant controls: design specs only (not contractors)
Construction risk: landlord's
Timeline risk: landlord's (with commencement contingencies)

Tenant savings vs. TI at $75/sf: $450,000 - $375,000 = $75,000
(IF actual cost equals landlord's estimate of $90/sf)

BUT: Landlord uses its own contractor at $90/sf
Tenant's contractor would have done the same work for $65/sf
Landlord's cost: $90/sf × 5,000 = $450,000
Tenant's cost if TI + own contractor: $325,000 (actual A1)
Tenant pockets $50K unused TI vs. turnkey "extra value": $0
Winner: TI allowance + efficient contractor = $50K better

OPTION C: VANILLA SHELL — NEGOTIATE TI TO COVER ALL
Space delivered: Vanilla shell (walls, electrical panel,
HVAC stubs, no finishes)
Full build-out from scratch required: $65/sf = $325,000
TI allowance covers: $75/sf = $375,000
Unused TI if pocketable: $50,000
Net cost to tenant: $0 (TI covers all build-out costs)
Plus: $50K pocketable = tenant effectively receives $50K

UNUSED TI NEGOTIATION VALUE SUMMARY
Unused TI ($50,000) if negotiated as rent credit:
Equivalent to 3.15 months of free rent
PV at 6% discount rate, applied in months 1-3: ~$49,200
Unused TI ($50,000) if negotiated as cash payment:
Value: $50,000 (immediate cash)
Unused TI ($50,000) if forfeited:
Value: $0
──────────────────────────────────────────────────────────────
KEY LESSON: A $50/sf TI gap between TI allowance and actual
build cost is worth up to $50,000 on a 5,000 sf deal.
This is negotiated in a single sentence at lease execution:
"Any unused portion of the TI Allowance may be applied
by Tenant as a credit against monthly Base Rent as it
becomes due." That sentence is worth $50,000.

TI Allowance vs. Turnkey vs. Vanilla Shell vs. As-Is: Full Comparison

Feature Turnkey TI Allowance Vanilla Shell As-Is
Who controls construction Landlord — selects contractors, manages project, delivers completed space Tenant — selects contractors, manages project, requests reimbursement Tenant — must build out from bare shell; sometimes with TI allowance Tenant — takes space in existing condition; no landlord build-out obligation
Landlord's financial commitment Open-ended cost commitment to a specification; landlord absorbs cost overruns (in true turnkey) Defined dollar cap per SF; tenant responsible for costs above cap Often includes TI allowance to cover build-out; sometimes no allowance (tenant-funded) No build-out commitment; may or may not include a small "paint and carpet" allowance
Construction risk Landlord's — cost overruns, contractor defaults, material delays Tenant's — responsible for staying within TI budget or funding overages Tenant's — full build-out cost and management burden Tenant's — any improvements above as-is condition are entirely tenant-funded
Timeline risk Landlord's — late delivery triggers rent commencement delay or termination rights Tenant's — construction delays extend tenant's timeline, not landlord's obligation Tenant's — tenant controls and bears risk of construction timeline None — tenant occupies space as-is; no construction period
Ability to pocket unused funds None — no "allowance" to underspend; landlord builds to spec and delivers Yes, if lease provides for it — unused TI is pocketable as rent credit or cash Yes, if TI allowance is provided and unused TI is pocketable per lease N/A — no allowance to pocket
Spec quality control Tenant must define specs precisely in the work letter — vague specs = lower-quality delivery Tenant-managed; tenant can use own contractors to achieve desired quality Tenant-managed; full control of quality and finishes None — must accept existing condition
Best for Tenants who want a finished space without construction management burden; smaller tenants without contractor relationships Tenants with existing contractor relationships or construction expertise who want cost control and flexibility Tenants starting from scratch in a new building who need maximum flexibility in space planning Tenants with no improvement needs; short-term users; tenants with very limited lease budgets
Typical market context Common for smaller spaces (<3,000 sf) in multi-tenant office buildings; landlord offers standard finish packages Standard for office spaces 3,000–25,000 sf; dominant structure in Class A and Class B markets Common in new construction; industrial-to-office conversion; ground-up retail development Subleases; short-term leases; second-generation retail; older industrial space

What Landlords Will (and Won't) Fund

Generally Fundable with TI Allowance

The TI allowance is designed to fund hard and soft costs associated with improving the physical space for the tenant's occupancy. Items that landlords typically permit as reimbursable TI costs include: Hard construction costs — demolition of existing conditions; new partition walls and framing; drywall, insulation, and ceiling work; doors, frames, and hardware; flooring (carpet, tile, hardwood, polished concrete); painting and wall finishes; millwork (built-in cabinetry, reception desks, credenzas, shelving); window treatments and blinds. MEP work within the premises — HVAC distribution (adding or modifying supply and return air distribution, VAV boxes, ductwork within the demised space); electrical panel capacity upgrades, circuit additions, and lighting; plumbing for sinks, coffee stations, bathrooms within the premises. Technology infrastructure — structured cabling (Cat 6/fiber runs) is increasingly accepted as a reimbursable cost; some landlords treat it as FF&E (not reimbursable); negotiate specifically for inclusion. Permit fees and inspection costs — building permits, plan check fees, and inspections required for the approved construction scope. Architect and engineer fees — most landlords reimburse design fees up to a defined cap (often 10–15% of hard costs).

Items Landlords Typically Won't Fund

Certain cost categories are almost universally excluded from TI reimbursement — not because they aren't legitimate project costs, but because they aren't improvements to the real property: Furniture, fixtures, and equipment (FF&E) — workstations, chairs, desks, conference tables, breakroom appliances, lockers, decorative art. These are tenant's personal property, not improvements to the leased space. Moving expenses — costs to relocate from an existing location to the new space. Signage — exterior and directory signage is typically covered by a separate signage allowance, not the TI; confirm this in the letter of intent. Branding and graphic elements — company logos, wall graphics, branded environmental elements are typically FF&E, not hard construction. Security systems and proprietary technology — access control systems installed by the tenant may be treated as personal property (removable at lease end) and excluded from TI. Costs incurred before lease execution — most leases require that TI-reimbursable costs be incurred after the lease is fully executed and the landlord has approved the construction plans; pre-lease design costs may be recoverable as part of the approved architect's fee, but costs incurred outside the approved scope are typically not.

Negotiating the Definition of Eligible Costs

The definition of eligible TI costs is negotiable, and the negotiation happens in the work letter (the exhibit to the lease that governs the build-out process). If technology infrastructure (cabling, server room construction), security systems, or certain FF&E (custom built-ins that are physically integrated into the structure) are important to your build-out economics, negotiate their explicit inclusion in the eligible cost definition. The landlord's objection to broad eligible cost definitions is typically that they don't want TI money used for personal property that the tenant will take with them at lease end — framing the requested inclusion as "improvements that become part of the building at lease expiration" is often persuasive.

Negotiating Maximum TI: The Key Levers

Lever 1: Lease Term Length

The landlord's willingness to invest in TI is directly correlated with lease term length — the TI is amortized over the lease term from the landlord's economic perspective, and a longer term reduces the annual per-square-foot amortization cost. A $75/sf TI allowance on a 5-year lease = $375,000 amortized over 60 months = $6,250/month. The same $75/sf TI on a 7-year lease = $375,000 over 84 months = $4,464/month — a 29% reduction in the landlord's monthly cost. Offering a longer initial term (or a longer committed term with defined early termination rights) directly supports a higher TI ask. The negotiating approach: ask for $90/sf TI with a 7-year term, then offer to accept $75/sf if the tenant can have a 5-year term. The landlord's math may actually prefer the longer term at lower per-month cost.

Lever 2: Credit Quality Documentation

The landlord's TI investment is functionally a loan: the landlord puts up capital at lease signing and recovers it through above-market rent over the lease term. A tenant who defaults and leaves in year 2 of a 7-year lease leaves the landlord with unamortized TI and no income to recover it. Higher-quality tenants — those with strong balance sheets, established operating history, and low default risk — justify higher TI commitments because the amortization risk is lower. If you're asking for above-market TI, support the request with strong financials: 3 years of audited or reviewed financial statements, a clean balance sheet, and a clear business case for the space. A tenant who provides 3 years of financial statements showing consistent growth and positive cash flow is more likely to receive a $90/sf TI ask than one who provides nothing and just asks for more.

Lever 3: Market Comparables

TI negotiation is fundamentally a market negotiation — what the landlord gives you should be informed by what comparable landlords are giving comparable tenants in comparable spaces. Your broker should provide you with actual comp data: TI allowances per square foot in recent transactions for similar space type, size, class, and submarket. Knowing that the three most recent Class B office deals in your submarket averaged $68/sf TI, while you're asking for $75/sf, gives you a credible basis for your ask. Knowing that competing buildings are offering $80/sf TI in a tenant-favorable market gives you even more leverage. Market data transforms the TI negotiation from a subjective discussion into an objective benchmark comparison — and landlords respond to market evidence.

Lever 4: Detailed Construction Budget

A landlord is more comfortable committing $375,000 in TI when they can see a detailed, line-item construction budget that accounts for every dollar. A tenant who says "we need $75/sf for our build-out" with no supporting documentation is making a claim the landlord can't evaluate. A tenant who provides a detailed budget — framing/drywall $45,000; HVAC $38,000; electrical $52,000; flooring $28,000; millwork $42,000; lighting $24,000; permits and fees $12,000; architect fees $24,000; contingency $10,000; total $275,000 — and asks for $75/sf "to provide a buffer for scope changes and material cost escalations" is making a professional, well-supported request that is much harder for the landlord to cut without specific objections.

The TI Draw Process: Mechanics and Common Mistakes

Standard Draw Request Requirements

Once construction is underway, the TI draw process is the mechanism by which the tenant requests reimbursement for documented construction costs. The typical draw process: Frequency — monthly draws are most common; some leases permit draws at defined construction milestones (foundation/rough-in complete, MEP rough-in complete, substantial completion). Documentation package — each draw request must include: (1) completed draw request form (landlord's form or AIA G702/G703 schedule of values); (2) contractor invoices for costs included in the draw; (3) conditional lien waivers from general contractor and all major subcontractors; (4) proof of prior draw disbursement (bank statements or cancelled checks showing contractor was paid from prior draw proceeds); (5) architect certification that work is complete per plans; (6) updated project cost summary. Landlord review period — typically 10–20 business days after receipt of a complete draw package; the lease should specify the review period and the remedy if the landlord fails to timely disburse an approved draw (typically interest on the delayed amount). Retainage — many leases require the landlord to hold back 10% of each draw as retainage until project completion and final lien waivers are received; negotiate to cap retainage at 5% or eliminate it for draws where work is fully complete and lien waivers cover the full draw amount.

Final Draw Requirements

The final TI draw — typically the last 10–20% of the total allowance — usually requires more documentation than interim draws: Certificate of occupancy (or temporary CO if final CO is pending) confirming the space is ready for occupancy. Unconditional lien waivers from the general contractor and all subcontractors who provided labor or materials to the project — confirming that all parties have been paid in full and waive any right to file a mechanic's lien against the property. As-built drawings — updated architectural drawings showing the space as actually constructed (reflecting any field changes from the approved plans). Warranty documentation — HVAC manufacturer warranties, appliance warranties, contractor workmanship warranties as required by the work letter. Punch list completion — a signed punch list confirming all outstanding items from the landlord's walk-through inspection have been completed.

TI Reimbursement Timeline Risks

The most common causes of TI reimbursement delays: incomplete draw packages (missing a single document restarts the landlord's review clock), landlord's internal approval process bottlenecks (institutional landlords with multiple sign-off levels can take 30+ days on a single draw), and disputed cost items (landlord questions whether a cost category is eligible, delaying the entire draw while the dispute is resolved). Build a realistic TI reimbursement timeline into your construction financing plan: if you're managing construction directly and funding costs before reimbursement, the gap between paying your contractor and receiving TI reimbursement can be 30–60 days. On a $375,000 project with monthly draws, the carrying cost of that gap at a 7% construction line rate is approximately $2,200/month — real cost that should inform whether to use a construction line of credit or fund construction from working capital.

6 Red Flags in Build-Out Allowance Negotiations

🛑 Red Flag 1: Accepting "Use It or Lose It" Without Negotiating the Unused TI Right

The default in most landlord-drafted lease forms is that unused TI is forfeited — the landlord reimburses only actual documented costs up to the cap, and any unspent balance stays with the landlord. Many tenants sign leases with this provision without realizing they've left real money on the table. On a 5,000 sf build-out where actual costs come in $10/sf below the TI cap, that's $50,000 forfeited. The negotiation is simple and costs nothing: "Any unused portion of the TI Allowance shall be applied as a credit against monthly Base Rent as it becomes due, with any remaining balance refunded to Tenant at lease commencement." This single sentence converts a forfeiture provision into a value capture. Landlords resist it — but it's a standard ask in tenant-favorable markets, and a well-represented tenant should always push for it.

🛑 Red Flag 2: A Turnkey Work Letter That Doesn't Define the Specification

A turnkey commitment is only as good as the specification it's based on. A work letter that says "landlord shall deliver the space in a fully built-out condition suitable for general office use" without defining finishes, HVAC capacity, lighting levels, electrical capacity, or ceiling height gives the landlord wide latitude to deliver a below-standard product that technically satisfies the commitment. Before signing a turnkey deal, require: (1) a detailed specification document listing finishes, brands, capacities, and quality standards for every major construction element; (2) a right to review and approve the construction plans before work begins; (3) a punch list right — the ability to identify deficiencies at substantial completion and require completion before accepting the space; (4) a warranty period — typically 1 year — during which the landlord is responsible for deficiencies discovered post-occupancy. A vague work letter is how tenants end up in a "builder-grade" finished office when they negotiated a $90/sf "premium" turnkey commitment.

🛑 Red Flag 3: No Landlord Disbursement Deadline or Interest Remedy for Late TI Payment

A TI allowance provision without a landlord disbursement deadline — and a remedy for failure to timely disburse — gives the landlord the ability to delay reimbursement indefinitely while the tenant carries the construction costs at its own expense. On a $375,000 project funded from a construction line at 7% annually, a 60-day landlord delay in disbursing a $100,000 draw costs the tenant $1,167 in carrying costs. Over multiple delayed draws, this can become significant. Negotiate: (1) a defined disbursement period (10–15 business days after complete draw request); (2) interest on any amount not disbursed within the required period at a defined rate (typically prime + 2%); and (3) a tenant offset right — if the landlord fails to pay an approved draw within a defined period (say, 30 days after the disbursement deadline), the tenant may offset the unpaid amount against the next month's rent. The offset right is the most powerful remedy because it eliminates the tenant's need to fund the shortfall from other sources.

🛑 Red Flag 4: TI Allowance Expiration Date That Doesn't Accommodate Realistic Construction Timelines

Many TI allowance provisions include an expiration date — a deadline by which the TI must be drawn or it expires (typically 12–18 months from lease commencement, or a specified date). Expiration dates that don't account for realistic permit timelines, landlord approval processes, and construction durations can catch tenants by surprise: if construction permitting takes 3 months, landlord approval takes 2 months, and construction takes 5 months, a project that should be drawing TI in month 10 of the lease may encounter difficulty meeting a 12-month TI expiration. Negotiate a TI expiration date that provides genuine flexibility: 24 months from lease commencement, or a more extended period for complex build-outs; and negotiate a right to extend the expiration if the delay is caused by landlord action (slow approval) or force majeure conditions.

🛑 Red Flag 5: No Lien Protection Framework in the Work Letter

When a tenant improves commercial space, the contractors and subcontractors who provide labor and materials to that project have the right to file mechanic's liens against the property if they aren't paid. In many states, a mechanic's lien against the property can cloud the landlord's title and create liability for the landlord — even though the landlord contracted with no one and owes the money to no one. Landlords protect themselves through lease provisions requiring the tenant to provide lien waivers from contractors before TI is disbursed. But a work letter that doesn't clearly establish the lien waiver process — when conditional waivers are required, when unconditional waivers are required, and what happens if a subcontractor files a lien — creates ambiguity that leads to TI disbursement holds and construction disputes. Establish the lien waiver workflow clearly in the work letter: conditional waivers with each draw request; unconditional waivers within 10 days of the construction payment being made; and the landlord's obligation to continue TI disbursement if the tenant provides required waivers timely.

🛑 Red Flag 6: Using the Landlord's Preferred Contractor in a "Turnkey" That's Really TI with Strings Attached

Some landlords offer what they describe as a "turnkey" build-out but structure it so that: the landlord's preferred general contractor does the work; the tenant's design preferences are accommodated within the contractor's pricing; and the landlord reimburses the tenant a fixed amount. This is really a TI allowance with a mandatory contractor — not a true turnkey. The risk: the landlord's preferred contractor may be more expensive than the market (because the landlord receives referral fees, has a long-standing relationship with below-average quality standards, or simply isn't competitive). The tenant loses the ability to solicit competitive bids and potentially pays $15–$25/sf more than necessary. Before accepting a "turnkey" with a specified contractor, request competitive bid data or the right to use your own contractor (with the landlord's approval) if the preferred contractor's pricing exceeds market by more than a defined threshold. Transparency in contractor pricing is the tenant's protection against captive-contractor markup.

✅ 12-Item Build-Out Allowance Negotiation Checklist

  1. Establish your actual construction cost estimate before negotiating TI: Know your baseline build-out cost per square foot before entering lease negotiations. A realistic, detailed construction budget is the foundation of the TI negotiation — without it, you're guessing at the right ask and can't evaluate the adequacy of landlord offers.
  2. Decide early whether you want TI allowance or turnkey — and know why: The right structure depends on your construction management capacity, contractor relationships, and preference for control vs. convenience. TI allowance gives you more control and the ability to capture savings; turnkey shifts risk and management burden to the landlord. Make a deliberate choice, not a default.
  3. Always negotiate a provision allowing unused TI to be applied as rent credit or cash: This is a single sentence worth up to $50,000 or more on a mid-size deal. Every tenant should ask for it on every deal. In a tenant-favorable market, it's often granted with minimal pushback. In a landlord-favorable market, even a compromise (unused TI applicable to FF&E or moving costs) is better than full forfeiture.
  4. Provide a detailed line-item construction budget with your TI ask: Support every TI ask with a specific, professional construction budget. A documented request is harder to cut than a bare number. It also positions you as a well-prepared tenant who knows what they're asking for and why — which builds credibility with landlords across the entire lease negotiation.
  5. Negotiate the eligible cost definition to include technology cabling and integrated FF&E: If structured cabling, access control, or custom built-ins are significant cost items in your project, negotiate their explicit inclusion in the TI eligible cost definition. The cost of this negotiation is zero; the benefit is potentially $15–$30/sf of qualifying costs that otherwise come out of pocket.
  6. Include a landlord disbursement deadline with an interest remedy and tenant offset right: A TI provision without a disbursement deadline gives the landlord free use of your construction costs during any payment delay. Require 10–15 business day disbursement, interest on late payments, and an offset right for amounts overdue beyond a defined cure period.
  7. Negotiate a TI expiration date of at least 24 months from lease commencement: Permit timelines, landlord approval processes, and construction durations routinely push projects to 12–18 months from lease commencement. A 12-month TI expiration is inadequate for anything other than the simplest cosmetic build-out. Build in genuine time cushion and a force majeure extension right.
  8. Establish the lien waiver workflow in the work letter before construction begins: Define exactly which lien waivers are required for each draw, when unconditional waivers must be provided after payment, and the landlord's obligation to continue TI disbursement if the tenant provides required documentation timely. A clear lien waiver process prevents the most common TI disbursement disputes.
  9. For turnkey deals, define the construction specification in writing with brand, finish, and performance standards: A turnkey commitment is worth the paper it's on only if the specification is precise. Get the finish level, HVAC capacity, electrical circuit counts, lighting levels, ceiling height, and flooring type documented in the work letter exhibit. "Office quality finishes" is not a specification.
  10. Request the right to approve any contractor substitutions in a turnkey deal: In a turnkey structure, the landlord controls contractor selection — but you should have approval rights over any material contractor substitution that might affect quality or timeline. Landlord-substituted subcontractors have no relationship with the tenant and no incentive to perform to the tenant's standards.
  11. Document the baseline building condition before construction begins: Photograph and document the as-delivered space condition before any construction starts. This protects you from disputes about damage caused during construction and establishes the baseline for restoration obligations at lease end. Date-stamped photo documentation takes 30 minutes and prevents expensive disputes later.
  12. Coordinate TI draw timing with construction payment terms to manage cash flow: If you're funding construction costs before reimbursement, model the cash flow gap between contractor payment and TI disbursement. A $375,000 project with 30-day contractor payment terms and 20-business-day TI disbursement creates 7–8 weeks of construction cost carry. Arrange a construction line of credit or working capital facility adequate to fund this gap before construction begins, not after.

Frequently Asked Questions

What is the difference between a TI allowance and a build-out allowance?
In most commercial real estate contexts, TI allowance and build-out allowance are used interchangeably — both refer to the landlord's financial contribution toward the cost of building out the leased space. The distinction that matters is between an allowance structure (tenant manages construction, landlord reimburses up to a defined cap) and a turnkey structure (landlord manages and funds construction, delivering a finished space). In a TI allowance deal, the tenant has control, bears construction risk, and may pocket unused funds. In a turnkey deal, the landlord controls construction, bears cost risk (in a true turnkey), and the tenant receives a finished space without construction management burden — but typically can't pocket any savings. The terms "build-out allowance" and "TI allowance" are functionally equivalent; what matters is whether the deal is structured as an allowance or a turnkey.
How do I negotiate the maximum TI allowance?
Four key levers: (1) Offer a longer lease term — landlords amortize TI over the term, so longer terms support higher TI; (2) Provide strong credit documentation — financial statements that demonstrate low default risk justify higher TI investment; (3) Use market comp data — know what comparable deals are getting in TI, and frame your ask relative to market; (4) Submit a detailed construction budget — a professional, line-item budget supporting your TI ask is much harder to cut than a bare number. Also: compare TI directly to rent abatement — if the landlord resists higher TI, ask whether equivalent value is available as additional free rent or rent reduction in early years. Many landlords who won't increase TI will provide equivalent value in rent concessions.
What will a landlord typically fund with a TI allowance?
Generally funded: hard construction costs (framing, drywall, ceilings, flooring, millwork, doors), MEP work within the premises (HVAC distribution, electrical, plumbing), life safety work (sprinkler modifications, fire alarm), permit fees, and architect/engineer fees (often capped at 10–15% of hard costs). Generally not funded: furniture, fixtures, and equipment (FF&E); moving expenses; signage (typically a separate allowance); proprietary technology systems; costs incurred before lease execution or outside the approved construction scope. Technology cabling and integrated custom built-ins are negotiable — fight to include them in the eligible cost definition if they represent significant project costs, framing the request as "improvements that become permanent fixtures of the space."
Can I keep unused TI allowance if construction comes in under budget?
Only if the lease says so — the default in landlord-drafted leases is "use it or lose it." Unused TI is forfeited if actual construction costs come in below the TI cap. This is a negotiable provision: tenants should always request that unused TI be applied as rent credit or refunded as cash. On a 5,000 sf project where construction comes in $10/sf below the cap, that's $50,000 at stake — a single sentence in the lease is worth $50,000. Even in landlord-favorable markets where full cash return isn't available, negotiate unused TI as rent credit, or redirect it to FF&E or moving expense reimbursement. Any recovery of unused TI is better than full forfeiture.
What is the TI draw process and what documentation is required?
The TI draw process: (1) Submit a draw request package to the landlord — typically monthly or at defined milestones; (2) Package includes: draw request form, contractor invoices, conditional lien waivers from GC and subs, proof of prior draw disbursement, architect certification, updated project cost summary; (3) Landlord reviews package — 10–20 business days for complete submissions; (4) Landlord disburses approved amount directly to tenant (or sometimes directly to contractor); (5) Final draw requires: unconditional lien waivers from all contractors, certificate of occupancy, as-built drawings, warranty documentation, and punch list completion certification. The most common draw delay: missing documentation. Organize the documentation requirements before construction begins and build lien waiver collection into the contractor payment workflow from day one.
What is a turnkey build-out and how does it compare to a TI allowance?
A turnkey build-out is a lease structure where the landlord commits to deliver the space in finished, ready-to-occupy condition to a defined specification. Landlord controls contractors, manages timeline, bears cost risk. TI allowance: tenant controls construction, bears cost risk above the cap, potentially pockets unused funds. Turnkey is better when: tenant lacks construction management capacity; the specification is clearly defined; the turnkey cost (per sf) is competitive with what tenant could build independently; and the landlord's construction timeline is reliable. TI allowance is better when: tenant has contractor relationships with favorable pricing; tenant wants to optimize for specific quality or efficiency standards; or there's meaningful likelihood of construction costs coming in below the TI cap (creating pocketable surplus). In markets where the turnkey rate ($90/sf) significantly exceeds what a tenant could build independently ($65/sf), the TI allowance structure at a lower per-sf amount can deliver greater net value.

Know Your TI Allowance Before You Negotiate

LeaseAI extracts and structures your TI allowance terms — eligible cost definitions, draw requirements, unused TI provisions, and disbursement deadlines — so you enter every negotiation knowing exactly what's on the table and what to push for.

Try LeaseAI Free →